What makes a good Application for Payment?

What is an Application for Payment?

An application for payment is an assessment of the works due to be completed up to the next payment due date. It is issued by the party that carried out the works to the party paying for the works. Generally, the application is issued a set number of days in advance of the payment due date. Whether or not there is a requirement for an application for payment to be issued within the (sub)contract, it is a good idea to get into the habit of issuing them. If the payer fails to issue their payment notice at the correct time, the application for payment will become the default payment notice and the sum detailed within becomes due on the final date for payment.

What should be included?

The most important element to be included within an application for payment is a breakdown of how the amount due has been calculated. However, that is only a bare minimum. A good application for payment will include the following:

  • A forecast final account figure;
  • The total amount due, including a detailed build-up to this amount;
  • The previously certified amount;
  • The net amount due; and
  • Previous application figures to show movement in the month.

It is also important to make sure the application is identified correctly. A good way to do this is by including a title of “Interim Application” with a sequential number at the end for ease of reference. Finally, including the Payment Due Date and the Final Date for Payment on the application ensures that the payer knows exactly what period of works the application refers to, and reminds them of when the payment is due to be made.

The build up to the amount due should be clear and easy to understand with no ambiguity. An easy way to achieve this is by separating the build-up into different sections like:

  • Contract/Measured Works;
  • Preliminaries;
  • Variations;
  • Dayworks;
  • Materials On/Off site (with requisite vesting certificates as required); and
  • Extension of Time / Loss & Expense / Acceleration.

Depending on the type of (sub)contract being used, the Contract/Measured Works section could be based on:

  • An activity schedule;
  • Milestone payments; or
  • A measured schedule of works, like a bill of quantities.

If the contract is remeasurable, it is important to detail out the remeasurement completed for the application. See below example showing 2 items that have been remeasured already and 1 that has not.

When it comes to putting together the build-up for variations, this should include at least budget figures for all changes and variations to the (sub)contract issued to the point of the application.

Forecast Final Account

Another aspect of interim applications that is really helpful is the forecast final account. The sooner you are able to start agreeing variations and remeasurements the better. It will allow you to have more certainty of the amount you are likely to be paid at the end of the project. That is why it is important to carry out any remeasurement as soon as you are able, and to try to include at least budget figures for all variations straight away. Including a forecast final account within your interim application should help to reduce the amount of time spent agreeing the final account after the works are completed, thereby enabling release of the final payment sooner.

VOLOCO can support your business producing Applications for Payment that drive commercial improvement. Book a call to see how we can support you.

Share on linkedin
Share on facebook
Share on twitter

Other posts

Learning
Mental Health Awareness Week – Loneliness
Learning
Tender Reviews and Risk Management
Dedicating the requirement amount of effort and investing in reviewing tenders before committing to submit is a proven strategy to identify, manage and reduce risk, potentially saving you wasted time and effort in the tendering process and even more significantly from entering into a deal that may be a bad one for you.
Learning
Package Procurement the Right Way
Procuring the work packages can make or break a construction project. Following the steps set out in this article will help reduce the risks associated with work package procurement, give you more control and ultimately improve your business performance.
Learning
Ensure You Insure
Insurance in building is not only prudent, but is also most likely a contract requirement and may be a legal requirement. Some deem it a “necessary evil” and others strongly believe in the protection of their business which it provides. Regardless, any builder without appropriate insurance risks the success of their business and potentially their personal assets.

Get in touch

Join our mailing list

To hear more from the team at VOLOCO, fill out the form below. By filling out the below for you are happy to receive occasional emails from the team.